Proposal

AI Campus Proposal

New generation AI PMDC solution: a 200 MW campus delivered as ten independent 20 MW units, engineered to the highest offshore structural class.

0MW Capacity 20 MW × 10 units
0Pcs Modules 2-tier loading capacity
0Racks Density High-density GPU cluster
Grade 9 Seismic Highest offshore class
Reading the Figures

What Those Four Numbers Commit You To

Headline figures on a campus proposal are only useful if you can see what follows from them. Each number below constrains the others, and together they set the density the whole facility has to be engineered for.

FigureWhat it fixesWhat it constrains downstream
200 MW totalThe grid connection the campus is negotiated against, and the size of the high-voltage receiving station on siteUtility lead time and the sectionalization of the medium-voltage loop that feeds each unit
10 units at 20 MWThe increment in which capacity is built, energized and soldCapital phasing, and the fact that no single fault or shutdown can take more than one tenth of the campus
368 modulesThe manufacturing volume and the shipping programme, stacked two tiers highFactory slot booking, transport permits and the crane and foundation work each landing needs
1,024 racksThe IT density the whole design is sized aroundCooling architecture, busway rating and the coolant temperatures the loop has to hold
~195kW Average per rack 200,000 kW across 1,024 racks. Derived from the figures above, and inside the 110 to 250 kW per rack band this platform is designed for.
2tiers Vertical stacking Two-tier loading roughly halves the land a given capacity occupies, which is what makes 200 MW fit a single campus boundary.
1/10 Maximum blast radius Because each 20 MW unit has its own power, cooling and IT PODs, the largest single thing that can fail is one unit.

Density is the parameter that drives everything else. At roughly 195 kW per rack, air cooling is not an option and the cooling loop stops being a service and becomes part of the primary structure of the building.

Data Center Masterplan

AI Campus Concept, 200 MW in Ten Units

Ten 20 MW PMDC units on one campus loop road, with dedicated high-voltage access, on-site substations and ancillary buildings.

Aerial masterplan render of the 200 MW AI campus with ten PMDC units
AI Campus Concept, data center masterplan render: 200 MW total capacity, 10 units, high-voltage access

Below: the same campus as a site plan.

POND HV ACCESS UNIT 01 · 20 MWUnit 01 · 20 MW PMDCUNIT 02 · 20 MWUnit 02 · 20 MW PMDCUNIT 03 · 20 MWUnit 03 · 20 MW PMDCUNIT 04 · 20 MWUnit 04 · 20 MW PMDCUNIT 05 · 20 MWUnit 05 · 20 MW PMDCUNIT 06 · 20 MWUnit 06 · 20 MW PMDCUNIT 07 · 20 MWUnit 07 · 20 MW PMDCUNIT 08 · 20 MWUnit 08 · 20 MW PMDCUNIT 09 · 20 MWUnit 09 · 20 MW PMDCUNIT 10 · 20 MWUnit 10 · 20 MW PMDC SUBSTATION MV YARD ANCILLARY 01 ANCILLARY 02 MAIN GATE
20 MW PMDC unitIndependent power, cooling and IT PODs. Each unit deploys and commissions without interrupting its neighbours.
HV receiving substationOwnership boundary, revenue metering and bus sectionalization feeding the campus MV loop.
MV distribution yardMain transformers and sectionalized MV buses distributing power to each 20 MW unit.
Ancillary buildingsOperations center, offices, spare-parts warehouse and staff facilities supporting 24/7 campus operations.
Delivery Strategy

Why Ten 20 MW Units and Not One 200 MW Build

A campus this size could be designed as a single facility. It is deliberately not. Independent units change the risk profile, the funding profile and the revenue profile at the same time.

Revenue starts before the campus finishes

Unit one can be energized, commissioned and let while units two through ten are still being built. Capital is not stranded waiting for a single completion date at the end of a multi-year programme.

One unit is the largest thing that can fail

Each 20 MW unit carries its own power, cooling and IT PODs. A fault, a shutdown or a planned maintenance window is contained inside one tenth of the campus rather than shared across all of it.

The tenth unit is built the same way as the first

A repeated 20 MW block is a manufacturing problem rather than ten separate engineering problems. Drawings, interfaces and acceptance tests are written once and reused, and each landing goes faster than the one before it.

Capacity can follow the grid, not lead it

Utility capacity rarely arrives all at once. Building in 20 MW increments lets the campus energize in step with what the connection can actually deliver, instead of holding a finished facility that cannot be powered.

The unit is the product, the campus is the arrangement. Ten units is the case shown here. The same block scales down to a single 20 MW site or up beyond 200 MW without redesigning what is inside it.

Core Design & Engineering Standards

Built to Outlast Its First Hardware Generation

Accelerator platforms turn over every few years. The shell, the structure and the coating system have to survive several of those cycles, because replacing them means taking capacity out of service. Three standards govern how long the campus stays serviceable.

Structure

Structural Durability, 25+ Year Life

Premium high-durability modular framework structures safeguard AI physical hardware while reducing long-term OPEX.

Why it mattersA 25 year shell outlives many generations of accelerator hardware. The structure is the one part of the facility that is not meant to be replaced.
Where the OPEX goesDurable framing shifts spend away from repeated structural remediation and toward the equipment that actually earns revenue.
Environment

ISO 12944 C5-M Corrosion Protection

Engineered for high humidity and marine environments, with maximum protection against salt spray and extreme atmospheric moisture.

What C5-M meansThe marine sub-class of the highest corrosivity category in ISO 12944. It is the specification written for coastal and offshore exposure, not for inland industrial sites.
How it is built upA heavy-duty system totalling 320 µm or more of dry film: 80 µm primer, 180 µm topcoat and a weathering clear coat over the top.
How it is verifiedDry film thickness is measured on the finished module, not assumed from the paint schedule.
Seismic

Grade 9 High-Standard Seismic Design

Incorporates seismic isolation bearings and shock-absorbent bracings to ensure uninterrupted runtime during seismic events.

Isolation bearingsBearings between the structure and its foundation absorb ground movement instead of transmitting it straight into the racks.
Shock-absorbent bracingBracing is detailed to dissipate energy rather than simply resist it, which is what keeps equipment mounted and piping joints intact.
The target is uptimeThe design case is not survival. It is a facility that is still running after the event, which is a materially harder requirement.

Secure. Reliable.

High Density. High Performance.

Built for the Future. Ready for Scale.

Lower OPEX. Maximum Uptime.